Little Falls, NY – February 17, 2026 – NASA is gearing up for a critical second wet dress rehearsal (WDR) for its Artemis 2 mission, the first crewed lunar flyby in over 50 years. The test, which begins today with a call to stations at the Launch Control Center, aims to iron out fueling issues that plagued the initial attempt earlier this month.

With the proposed launch now pushed to at least March 2026, this rehearsal is pivotal in ensuring the Space Launch System (SLS) rocket and Orion spacecraft are ready to carry four astronauts—Reid Wiseman, Victor Glover, Christina Koch, and Jeremy Hansen—on a 10-day journey around the Moon.

Recap of the First Wet Dress Rehearsal

The first WDR took place on February 2-3, 2026, at Launch Pad 39B at NASA’s Kennedy Space Center in Florida. This prelaunch test simulated fueling operations by loading over 700,000 gallons of cryogenic propellants—liquid oxygen and liquid hydrogen—into the SLS rocket’s tanks.

Teams also practiced Orion spacecraft closeout procedures, including hatch closure by a ground crew, and ran through a full countdown sequence.

However, the test encountered a familiar setback: a liquid hydrogen leak at the tail service mast umbilical (TSMU) interface, located at the base of the rocket where flight and ground systems connect.

The leak, which hovered around 12-14% for much of the fueling, spiked above NASA’s 16% safety limit during the terminal countdown phase, when the core stage was pressurized. This forced engineers to halt the simulation at T-5 minutes and 15 seconds, preventing a full run-through to T-0.

The issue echoed problems from the 2022 Artemis 1 mission, but NASA officials emphasized that WDRs are designed to uncover such anomalies. Post-test analysis revealed a faulty seal in the TSMU cavity, which teams addressed on-site without rolling the rocket back to the Vehicle Assembly Building (VAB).

A subsequent confidence test on February 12 confirmed lower leak rates, and a clogged filter in ground support equipment was replaced to resolve the slower-than-expected hydrogen fill rate. Despite these challenges, the test achieved key objectives, including full propellant loading and safe tank drainage.

Plans for Today’s Second Wet Dress Rehearsal

Launch controllers are set to begin the nearly 50-hour countdown sequence at 6:40 p.m. EST today, February 17. The actual tanking operations—loading the cryogenic fuels—will occur on Thursday, February 19, culminating in a simulated launch at 8:30 p.m. EST with a four-hour test window.

This rehearsal will mirror the first but incorporate lessons learned, including enhanced monitoring of TSMU seals and propellant flow rates.

Key activities include:

  • Fueling the SLS: Loading liquid oxygen and hydrogen into the core stage and interim cryogenic propulsion stage, testing for leaks and pressurization stability.
  • Countdown Simulation: Running a full launch countdown, demonstrating clock recycling, and practicing scrub procedures by draining the tanks.
  • Orion Closeout: A ground team will head to the pad to seal the spacecraft’s hatches and verify environmental controls, though the Artemis 2 crew will not participate.

NASA will provide live updates via its blog and streaming feeds, with dedicated camera views during tanking. The agency has stressed a cautious approach, with Administrator Jared Isaacman noting, “We should not be surprised” by fueling hurdles given the SLS’s complexity.

Impact on the March Launch Schedule

The need for a second WDR has directly delayed the Artemis 2 launch from potential February windows to no earlier than March 6, 2026.

NASA recently expanded the March opportunities to allow more time for data review and any additional fixes. A successful rehearsal could confirm the rocket’s readiness, but officials won’t set a firm date until all data is analyzed.

This timeline shift also accounts for ongoing refinements, including a modified reentry trajectory for Orion to mitigate heat-shield charring observed during Artemis 1. If issues persist, further delays could push the mission later into March or beyond, but NASA remains optimistic about meeting its goals for sustainable lunar exploration.

Artemis 2 represents a milestone in NASA’s broader Artemis program, testing systems for future Moon landings and paving the way for diverse crews, including the first woman and first person of color on a lunar mission.

As the countdown begins today, space enthusiasts worldwide are watching closely for updates on this historic endeavor.