Kennedy Space Center, Florida – February 3, 2026 – NASA teams concluded a critical wet dress rehearsal for the Artemis II mission yesterday, uncovering several technical issues that have prompted a delay to the planned launch window. The test, which simulated fueling and countdown procedures for the Space Launch System (SLS) rocket and Orion spacecraft, aimed to ensure all systems were ready for the first crewed lunar-orbit mission since Apollo 17.

The rehearsal began on January 31, 2026, at 8:13 p.m. EST, spanning approximately 49 hours at Launch Pad 39B. During the procedure, engineers powered up the SLS core stage and the interim cryogenic propulsion stage, then loaded more than 700,000 gallons of super-cold liquid oxygen (LOX) and liquid hydrogen (LH2) into the rocket’s tanks. This “wet” test – so named because it uses actual propellants – included transitioning to fast-fill modes, topping off tanks, and entering a terminal countdown to simulate launch-day operations.

A five-member team was dispatched to the pad to perform closeout tasks on the Orion spacecraft, including retorquing a valve on the crew module hatch and purging the service module cavities with breathing air rather than gaseous nitrogen to ensure safety. The countdown reached T-5:15 when the ground launch sequencer automatically halted it due to a spike in liquid hydrogen concentration at the tail service mast umbilical interface. This leak echoed earlier issues during tanking, requiring troubleshooting steps like stopping propellant flow, warming seals, and adjusting loading procedures.

Additional challenges included cold weather impacts on cameras and equipment, extended closeout times, and intermittent audio dropouts among ground teams. Despite these hurdles, NASA officials noted that the test achieved several objectives, including successful tank filling and safe propellant draining afterward. “These rehearsals are designed to find and fix problems before we put our crew at risk,” said Artemis Launch Director Charlie Blackwell-Thompson during a post-test briefing.

Based on the findings, NASA has decided to conduct a second wet dress rehearsal after reviewing the data and implementing fixes. This has shifted the launch opportunity from an original February target to March 2026 at the earliest. The new potential windows include:

  • March 6, 2026, at 8:29 p.m. EST (120-minute window)
  • March 7, 2026, at 8:57 p.m. EST (120-minute window)
  • March 8, 2026, at 10:56 p.m. EDT (120-minute window)
  • March 9, 2026, at 11:52 p.m. EDT (120-minute window)
  • March 11, 2026, at 12:48 a.m. EDT (115-minute window)

The delay also affects the Artemis II crew – Commander Reid Wiseman, Pilot Victor Glover, Mission Specialist Christina Koch, and Mission Specialist Jeremy Hansen – who entered quarantine on January 21 but have now been released, with plans to re-enter about two weeks before the new launch date. NASA emphasized that prioritizing safety is key to the Artemis program’s goal of returning humans to the Moon and paving the way for Mars exploration.